⚠️ Under Development — Expect Mistakes and Errors · Pre-Feasibility Draft, October 2026
Notebook
17
InfrastructureModelled

Dam Engineering Design

RCC gravity · FSL 1,435m · 45m height · 970m crest · 90.9 Mm³ storage · pre-feasibility ±30%

45 m
foundation to crest
Dam height
970 m
30m DEM cross-section
Crest length
90.9 Mm³
3.0× MAR
Active storage
21.3 Mm³/yr
post-evaporation
Net yield
550 m³/s
Q₁₀₀₀ design
Spillway flood
100 km
gravity, 1,435m head, zero pumping
Pipeline

Pre-Feasibility Engineering Drawings

Four panels computed from the 30m Copernicus DEM and 90m catchment DEM: valley cross-section at dam axis · RCC gravity dam cross-section · reservoir hypsometric (area- and volume-elevation curves) · net yield vs FSL sensitivity analysis.

Sheikh Highland Dam pre-feasibility engineering drawings

NB17 · Generated Oct 2026 · 30m Copernicus GLO-30 DEM · 90m corridor clip · pysheds DAM-01 catchment

Valley Cross-Section at Dam Axis

30m Copernicus DEM scanned ±3.1 km E–W across the valley at 9.781°N. The valley is asymmetric V-shape: gentle west slope (~1V:7H) formed by a broad highland plateau, steeper east slope (~1V:3H) where the Golis Range escarpment rises sharply.

Height above thalwegWater level (m ASL)Valley width
+10 m1,405 m493 m
+20 m1,415 m (dead storage level)709 m
+30 m1,425 m832 m
+40 m1,435 m = FSL894 m
+45 m1,440 m = crest913 m
+50 m1,445 m987 m
+70 m1,465 m1,110 m
30m DEM resolution · Width is contiguous valley connected to thalweg · Values ±5% due to pixel resolution

Why RCC Gravity Dam

Rocky Precambrian basement

The Golis Range at 1,400 m ASL is Precambrian basement complex — excellent foundation bearing capacity and nearby quarry for aggregate. No soft valley alluvium.

Valley width rules out arch

Valley width at FSL is 894 m. Width/height ratio = 894/40 = 22 — too wide for an arch dam (requires W/H < 4). Gravity or embankment only.

RCC vs earthfill at this width

An earthfill dam (1V:3H slopes) at 894 m width and 45 m height requires ~16 Mm³ of fill vs 0.86 Mm³ of RCC. Remote site logistics favour the more compact RCC option.

Dry-season construction

Somaliland dry season (October–February) gives a 5-month construction window without river diversion issues. RCC continuous-pour is faster than embankment compaction.

Reservoir: Area, Volume & Evaporation

FSL (m)Height (m)Area (km²)Volume (Mm³)Evap lossNet yield
1,405+100.532.20.6 Mm³/yr29.3 Mm³/yr
1,415+20 (dead)1.6712.61.8 Mm³/yr28.1 Mm³/yr
1,420+252.9324.23.2 Mm³/yr26.7 Mm³/yr
1,425+304.3942.54.8 Mm³/yr25.1 Mm³/yr
1,430+356.1168.76.7 Mm³/yr23.2 Mm³/yr
1,435 ✓+40 (FSL)7.84103.68.6 Mm³/yr21.3 Mm³/yr
1,440+459.84147.810.8 Mm³/yr19.1 Mm³/yr
1,445+5011.97202.313.2 Mm³/yr16.7 Mm³/yr
1,465+7024.19553.726.6 Mm³/yr3.3 Mm³/yr
Net yield = gross MAR 29.9 Mm³/yr − net evaporation (lake 1.50m − land ET 0.40m = 1.10 m/yr × area). Assumes GPM IMERG rainfall (341mm) and CN=0.20. See MAR sensitivity table below for the full uncertainty range. FSL=1,435m selected: 2× MAR active storage, maximum net yield vs regulation trade-off.
The evaporation trap

A larger reservoir always has lower net yield because every extra km² of water surface loses ~1.1 m/yr to net evaporation. At FSL = 1,465 m the reservoir is 24 km² and loses 26.6 Mm³/yr — nearly all of the 29.9 Mm³/yr inflow. The recommended FSL = 1,435 m balances storage (90 Mm³, 3-year drought cover) against delivery (21 Mm³/yr net).

Hypsometric note on 90m DEM

The reservoir area/volume curve uses the 90m DEM clipped to the pysheds DAM-01 catchment (439 km²). At 90m resolution the reservoir boundary is approximate (±500m at the upstream limit). LiDAR/UAV survey (5cm DTM, ToR B) will refine this by ±10–15% at bankable feasibility stage.

Rainfall & Runoff — Data Sources and Uncertainty

The project has two independent satellite rainfall datasets that disagree by 18%. The runoff coefficient (CN) — the fraction of rainfall that becomes streamflow — has not been measured; no stream gauge exists on the Sheikh River. The table below shows Gross MAR across the full plausible range. The design uses GPM IMERG × CN=0.20 (yellow row). All other rows represent genuine uncertainty.

Source A — GPM IMERG (used)
341 mm/yr · 23-year climatology 2001–2023 · NASA GPM DISC · Downloaded /data/gpm_imerg_annual_climatology.csv
Source B — CHIRPS v2.0
403 mm/yr · 24-year climatology 2000–2023 · NOAA/UCSB · Downloaded /data/chirps_annual_2000_2023.csv
CNTerrain descriptionMAR — GPM 341mmMAR — CHIRPS 403mm
0.10Karst limestone, deep percolation14.9 Mm³/yr17.7 Mm³/yr
0.15Sparse semi-arid shrubland (lower bound)22.4 Mm³/yr26.5 Mm³/yr
0.20 ★FAO semi-arid standard (design basis)29.9 Mm³/yr35.4 Mm³/yr
0.30Rocky Highland, sparse cover44.9 Mm³/yr53.1 Mm³/yr
0.40Highland grassland, thin soils59.9 Mm³/yr70.8 Mm³/yr
MAR = 439 km² × P × CN / 1,000. Catchment area 439 km² is from Copernicus DEM + pysheds (high confidence). The uncertainty is entirely in P and CN.
CNNet yield — GPMNet yield — CHIRPSCovers Phase 2 demand?
0.106.3 Mm³/yr9.1 Mm³/yr✗ Deficit −15 Mm³/yr
0.1513.8 Mm³/yr17.9 Mm³/yr✗ Short −7 to −3 Mm³/yr
0.20 ★21.3 Mm³/yr26.8 Mm³/yr✓ Just meets / exceeds
0.3036.3 Mm³/yr44.5 Mm³/yr✓ Comfortable surplus
0.4051.3 Mm³/yr62.2 Mm³/yr✓ Large surplus
Net yield = Gross MAR − 8.6 Mm³/yr (net evaporation at FSL 1,435m). Phase 2 agricultural demand from dam: 21 Mm³/yr. The design sits at the minimum viable CN.
Critical finding — design is at minimum viable CN

At CN=0.20 / GPM, net yield (21.3 Mm³/yr) exactly equals Phase 2 agricultural demand. There is zero carry-over margin if CN is 0.15 or lower. The Golis Range is partly limestone — karst percolation could push the effective CN to 0.10–0.15. ToR A stream gauging (18 months) is the highest-priority study before dam construction funding is sought.

What ToR A will resolve
  • ·Install 2 stream gauges on Sheikh River (wet + dry season runs)
  • ·Calibrate CN against measured flow events
  • ·Reconcile GPM vs CHIRPS using rain gauge network
  • ·Reduce MAR uncertainty from ±60% to ±15%
  • ·Assess whether dam upsizing to FSL 1,445m is warranted at lower CN
  • ·Confirm Q₁₀₀₀ design flood (currently Rational method, unverified)

RCC Gravity Dam — Structure

Geometry

Foundation level1,392 m ASL (3m trim below thalweg)
Thalweg / MWL1,395 m ASL
Full Supply Level1,435 m ASL (+40 m structural)
Crest elevation1,440 m ASL (+45 m total height)
Crest length970 m
Crest width8 m (maintenance road)
Base width31.5 m (0.70H)
Upstream faceVertical + 2.2 m base kick (0.05H)
Downstream slope1V : 0.47H

Materials

RCC dam body862 × 10³ m³
Portland cement78,600 t
Fly ash (30%)62,900 t
Local aggregate1,573 × 10³ t (quarry on abutment)
CVC upstream face33 × 10³ m³ (0.8m thick)
Reinforcing steel2,642 t (CVC face only)
Foundation excav.92 × 10³ m³
Cutoff / grouting2,400 m of drill holes
Spillway concrete~2,500 m³ (ogee + chute)

Hydraulics

Catchment439 km² (NB16 pysheds)
Tc (time of conc.)14 h (Kirpich, 30 km reach)
Q₁₀₀₀566 m³/s (Rational method)
Q_PMF849 m³/s (1.5 × Q₁₀₀₀)
Spillway typeOgee weir + chute + flip bucket
Spillway length85 m (5 spans × 15 m)
Spillway crest1,435 m ASL (= FSL)
Design head2.5 m → Q₁₀₀₀ passes
PMF head3.5 m → 1.5 m freeboard
LocationRight (east) abutment

Outlet Works & Gravity Pipeline

Intake tower & conduit

ComponentSpecification
Intake tower height35 m reinforced concrete tower
Bottom draw-off port1,400 m ASL (+5 m above thalweg)
Top port1,435 m ASL (= FSL)
Draw-off levels3 ports: environmental / operational / emergency
Outlet conduit2 × DN800 mm steel pipe (redundancy)
Conduit length80 m through dam body
Control valvesButterfly + needle valve each barrel
PRV requirementPressure-reducing valve downstream — 35m head
Operating flow0.68 m³/s = 58,700 m³/day at net yield
PRV required: full gravity head (35m at dead pool to 40m at FSL) gives 16+ m/s velocity in DN800 — flow controlled by PRV and pipeline demand at Berbera.

Gravity pipeline to Berbera

ParameterValue
RouteSheikh Highland → Sheikh Pass → Berbera coast
Length100 km (road corridor alignment)
DiameterDN1200 mm steel, FBE internal lining
Gravity head1,435 m (FSL to Berbera coast 0 m)
Pumping energyZero — full gravity
Design velocity~2.0 m/s (controlled by PRV at Berbera)
Max capacity~2.3 m³/s = 200,000 m³/day (hydraulic limit)
Operating capacity58,700 m³/day (21.3 Mm³/yr net yield)
ConnectionSWRO intake header at Berbera desalination plant
Pipeline alignment100 km, road corridor, remote mountain
Same route as NB12 water pipeline backbone. Dam gravity pipeline shares the Sheikh Pass road corridor with the regional water distribution main.
Pre-feasibility accuracy caveat

This design is at pre-feasibility level (±30%). Key uncertainties: (a) actual valley width from LiDAR (±20% effect on crest length and RCC volume); (b) foundation rock quality from boreholes (±15% on grouting); (c) pipeline alignment survey (±10% on pipeline length). Bankable feasibility study with ToR A/B/C surveys will bring accuracy to ±10%.

Geotechnical & Environmental Notes

Foundation geology
  • Precambrian basement complex (typical Golis Range)
  • Expected: Granitic gneiss / metamorphic rock
  • Good bearing capacity: 3–5 MPa allowable
  • Curtain grouting for seepage control
  • Confirm by 3 × core boreholes at dam axis (ToR B)
Seismicity
  • Gulf of Aden rift zone — moderate seismicity
  • USGS: Mw 6.0 expected, Mw 6.5 MCE
  • Dam designed for MCE 0.15g PGA
  • Base width 0.70H provides seismic stability margin
  • Full seismic hazard assessment required (ToR A)
Environmental & social
  • Highland plateau: very low population density
  • No major settlements within reservoir footprint (est.)
  • E&S budget (4%) covers ESIA + RAP
  • Reservoir 7.84 km² — limited displacement impact
  • Environmental flow: 0.2 m³/s minimum release

Path to Bankable Feasibility

ToRStudyDurationUnlocks
ToR AHydrological study: stream gauges, flood analysis, seismic hazard18 monthsMAR ±10%, design flood confirmed
ToR BGeotechnical: 3 core boreholes at dam axis + UAV/LiDAR DTM12 monthsFoundation design, reservoir volume ±10%
ToR CESIA + RAP: social census, environmental baseline, resettlement plan12 monthsADB/IDA/IsDB safeguard compliance
ToR DDetailed engineering design (DED): dam, spillway, pipeline24 monthsTender-ready drawings, BOQ ±10%
—Tender and award12 monthsConstruction start
All four studies required before any DFI (AfDB / IDA / IsDB) will move to appraisal.

Reservoir Inundation Extent — FSL 1,435 m

The hatched blue area shows the 7.72 km² inundated at Full Supply Level (1,435 m ASL). Computed by flood-filling 90m DEM cells between thalweg (1,395 m) and FSL within the pysheds DAM-01 catchment boundary (439 km²). Toggle satellite imagery to assess terrain and land cover within the inundation footprint.

Your feedback on this notebook

0/1000 characters

Your feedback is read by the Berbera planning team. All submissions are treated with respect.