⚠️ Under Development — Expect Mistakes and Errors · Pre-Feasibility Draft, October 2026
Notebook
18
InfrastructureModelled

SWRO Desalination Plant Siting

Western Headland W2 · 44.933°E · 8.6 km from urban core · not airport side · score 4.70/5.0

W2
Western Headland
Selected site
4.70/5.0
vs E1 existing: 2.65/5.0
Siting score
8.6 km
from town centre
Urban separation
500k m³/d
expandable modular
Phase 3 capacity
7.1 km
coastal trunk main
Pipeline to city
70 ha
1,000 m × 700 m
Plant footprint
⚡ NB19 supersedes this page — Carabeyto Calinuur gallery intake now recommended

NB19 extended the siting analysis to 9 criteria and identified a subsurface gallery intake at the Wadi Calinuur estuary (44.680°E) that eliminates UF pre-treatment entirely and achieves zero marine entrainment. W2 Western Headland (this page) is superseded. See NB19 — Carabeyto Calinuur SWRO Site.

NB18 Oct 2026 — Site revised from E1 (east) to W2 (west)

The provisional SWRO site at [45.055°E] was on the airport corridor side (Z4 Eastern Strip) — contrary to planning requirements. NB18 runs a 6-criteria weighted siting analysis across 4 candidates. The recommended site is W2 Western Headland at 44.933°E, 10.462°N: 8.6 km west of the urban core, on the open Gulf of Aden coast, away from both the urban area and the airport corridor. Score: 4.70/5.0 vs 2.65/5.0 for the rejected E1.

Multi-Criteria Siting Analysis

Six weighted criteria scored 1–5 across four candidate sites. Airport corridor avoidance (20% weight) immediately eliminates E1. Water quality (25%) and urban distance (20%) drive W2 above W3. Pipeline cost (10%) keeps W3 from winning despite its greater distance.

SWRO coastal siting analysis — NB18

NB18 · October 2026 · 6-criteria weighted analysis · Peninsula schematic from known coordinates

Candidate Site Comparison

SiteLocationDist. urbanAirport side?Score
W2 ★44.933°E — Western Headland8.6 kmNo — open Gulf coast4.70/5.0
W344.905°E — Far Western Coast11.6 kmNo4.25/5.0
W144.965°E — Inner Western Coast5.3 kmNo3.80/5.0
E1 ✗45.055°E — Eastern Strip (old)6.4 kmYES — rejected2.65/5.0
W2 selected: best balance of water quality, urban separation, brine dispersal, and pipeline cost. W3 scores higher on distance but adds 4km of coastal pipeline.

Scoring criteria (weighted)

CriterionWeightW2 scoreRationale
Water quality25%5/5Open Gulf of Aden — no port or urban runoff influence
Urban distance (≥4km)20%5/58.6km — well above the 4km threshold
Not airport side20%5/5West of urban core; airport (HCBE) is 26km east
Brine dispersal15%5/5Open coast; Gulf westward current disperses plume offshore
Land availability10%4/570ha coastal flat; slight terrain relief on headland
Pipeline cost10%3/57.1km to distribution node — moderate; W1 closer but water quality lower
Weighted total: 4.70/5.0. All top-3 criteria score 5/5 for W2.

Why W2 Western Headland

Open Gulf of Aden — best intake water quality

The western coast faces the open Gulf of Aden with no harbour influence, port traffic, or urban runoff. Salinity is stable at ~35.5 g/L (vs harbor values of 36–38 g/L due to evaporation). Lower suspended solids reduces pre-treatment cost (UF membranes) and extends RO membrane life.

Gulf westward current — brine dispersal

The Gulf of Aden has a dominant westward surface current (~0.5–0.8 m/s). Brine discharged at W2 (60 g/L concentrate) is swept westward away from the city and diluted rapidly. A 300m offshore diffuser at 25m depth achieves <39 g/L within 500m of discharge.

8.6 km separation from urban core

SWRO plants generate noise (intake pumps, ERDs, chemical storage) and visual impact. The 8.6km separation places W2 well outside the 4km noise/odour buffer typical for Gulf SWRO plants. The site is outside the urban planning boundary and requires no resettlement.

Not airport side — planning compliance

HCBE Berbera International Airport is at 45.159°E — the eastern end of the planning area. Zone Z3 "Airport & Industrial Corridor" and Z4 "Eastern Coastal Strip" are reserved for port logistics, industrial estates, and tourism. W2 (44.933°E) is firmly in the western coastal lowland, compatible with Z2 industrial coastal use.

Plant Design Parameters — W2 Site

Intake System

Intake typeOpen sea intake (direct)
Intake depth25m depth, 200m offshore
Design flow (P3)1.0 m³/s (86,400 m³/hr)
Screen typeTraveling band screens, 1mm mesh
Salinity35.5 g/L (Gulf of Aden open)
Temperature27–32°C (seasonal)
SDI target<3 (UF pre-treatment)
Intake pump head25–30m (submersible)

RO Process

Phase 1 capacity50,000 m³/day
Phase 3 capacity500,000 m³/day
Recovery rate45% (Gulf high-salinity)
Brine concentrate64 g/L (45% recovery)
Energy (net)3.5 kWh/m³ (with ERD)
ERD typePressure Exchanger (isobaric)
Membrane typeSpiral wound SWRO, 8" elements
Pre-treatmentUF + cartridge filter
Post-treatmentRemineralisation + Cl₂

Brine & Outfall

Outfall typeMultiport diffuser, 300m offshore
Outfall depth30m (below thermocline)
Dilution ratio1:20 (initial mixing)
Concentrate conc.64 g/L → 40 g/L at 500m
DispersionGulf westward current 0.5–0.8 m/s
Marine buffer500m exclusion zone (fishing)
Discharge velocity>3 m/s (forced mixing)
Permit neededNEPA Somaliland + ESIA

W2 Site Location — Live Map

W2 Western Headland at 44.933°E, 10.462°N — 8.6 km west of urban core, 7.4 km west of port. The 70 ha plant footprint (1,000 m × 700 m) is shown as the polygon. Toggle satellite imagery to view coastal terrain and land cover. Click the site marker for properties.

Pipeline & Energy Connection

Route segmentLengthSpecification
SWRO W2 → coastal trunk junction7.1 kmDN1000 mm, coastal flat, gravity-assisted
Coastal trunk → Berbera city header3.2 kmDN1200 mm, existing alignment NB12
City header → Z1 Urban Core2.5 kmDN800 mm distribution main
Coastal trunk → Sheikh pipeline off-take2.8 kmDN1000 mm, joins highland gravity line
TOTAL to distribution~16 kmAll coastal alignment, no mountain tunnels
7.1km coastal pipeline from W2 to existing NB12 backbone — coastal flat, gravity-assisted alignment.
D3 — Hargeisa gravity extension (NB12 Oct 2026)

NB18 confirmed the dam site at 1,395m ASL. This creates a gravity-flow opportunity to Hargeisa (1,334m) — 61m head over 115.3km (grade 0.53‰). The D3 Hargeisa gravity main (DN900 HDPE PE100, 115.3km) was added to the NB12 pipeline network with no pumping required. Capacity: 110,000 m³/day. Phase 2 demand: 56,000 m³/day (Hargeisa, 700k pop.).

Power supply to W2

W2 is 8.6km west of the main solar farm grid connection at SS-01. A 33kV spur from the coastal grid ring serves the SWRO plant. Phase 3 SWRO load: 500,000 m³/day × 3.5 kWh/m³ = 72.9 MW. The NB11 solar system (963 MW total) has capacity to serve this load. Dedicated SWRO substation (SS-SWRO): 132 kV / 33 kV, 100 MVA.

Studies required before bankable feasibility
  • · Bathymetric survey (MBES) at W2 — confirm 25m depth within 200m
  • · Coastal current survey (ADCP, 12 months) — confirm westward drift pattern
  • · Marine ecology baseline — coral, seagrass, fisheries within 1km
  • · Geotechnical: substrate type for intake pipe trench
  • · Brine dispersion modelling (CORMIX or MIKE 21)

Your feedback on this notebook

0/1000 characters

Your feedback is read by the Berbera planning team. All submissions are treated with respect.