Structure Plan

Land use plan · Transport network · Utility corridors · Green network · Phase 1–3 spatial sequence

5,597 ha
developed + reserved
Urban land
250 km
paved target Phase 2
Road network
860 ha
parks + buffer + coast
Green network
42 km
reserved ROW
Utility corridors

Transport Hierarchy

ClassWidthLengthSpeedStandard
Expressway (port access)30m ROW12 km80 km/h2+1 lanes, grade separated junctions
Primary arterial24m ROW38 km60 km/h2+2 lanes, signalised intersections
Secondary collector18m ROW85 km50 km/h1+1 lanes, roundabouts
Tertiary local12m ROW115 km30 km/h1+1 lanes, shared surface
Promenade / active travel8m ROW12 kmPedestrianNo vehicles
All primary and secondary roads include kerbed drainage and footpath. See NB07 for NetworkX bottleneck analysis.

Public Transport Framework

BRT Corridor 1
Port Gateway → Old Town → Berbera Central → BEZ
5-min peak headways
BRT Corridor 2
Port → Airport → Residential Zones → Sheikh Road
10-min peak headways
Minibus network
All secondary routes on fixed routes
15-min headways

Green Network

The Structure Plan reserves 860 ha as permanent green infrastructure: coastal buffer, linear parks along drainage corridors, neighbourhood parks, and the escarpment conservation zone.

Green areaHaFunction
Coastal promenade buffer85Ecology + recreation
Escarpment conservation340Watershed protection
Wadi (drainage) greenways180Flood + ecology
Neighbourhood parks (×7)95Active recreation
Berbera Central Square1.2Civic focus
BEZ green buffer158Industrial screen
TOTAL860—

Utility Corridor Reservations

SWRO → Sheikh pipeline
20m ROW
320 km
High voltage transmission
30m ROW
12 km (city ring)
Fibre optic backbone
3m ROW (shared)
85 km
Sewerage trunk main
6m ROW
18 km

Phase Spatial Sequence

Phase 1 (2026–30)
  • ·Berbera urban core (Z1–Z4)
  • ·Port access expressway
  • ·BEZ Phase 1 roads
  • ·SWRO intake and plant site
  • ·Solar farm site (345 MW)
  • ·Promenade + Old Town
Phase 2 (2031–35)
  • ·Z5 residential medium zones
  • ·Sheikh road upgrade
  • ·Burco pipeline ROW
  • ·Secondary arterials (complete)
  • ·Airport upgrade
  • ·BEZ Phase 2 extension
Phase 3 (2036–40)
  • ·Z7 growth reserve release
  • ·Sheikh urban nodes
  • ·BEZ Phase 3 industrial
  • ·Sheikh–Burco urban corridor
  • ·CSP site (219 MW)
  • ·Smart city infrastructure