Infrastructure Gaps

Current vs. required infrastructure across water, power, roads, and wastewater · NetworkX network analysis

0%
today → 100% by 2030
Piped water coverage
30–50%
today → 100% by 2028
Power coverage
18 km
today → 250 km by 2035
Paved roads
None
→ full sewerage Phase 2
Wastewater

Water Supply Gap

Now: Trucked water from 2 kiosks. USD 8–12/m³. Intermittent. 6–10 hrs/day in some areas.
Target: Piped SWRO water to every household. 24 hrs/day. USD 0.55/m³. 500k m³/day capacity by Phase 3.
Gap: Full piped distribution network required across all 7 zones. DN600 mains → DN200 service connections.
→ Engineering detail in NB12

Power Supply Gap

Now: Diesel generators, 30–50% coverage. Daily load-shedding. Average cost USD 0.35–0.45/kWh.
Target: 100% solar electricity. LCOE USD 0.025/kWh. BESS backup. 963 MW Phase 3.
Gap: 1,400 km of LV/MV distribution cabling. 18 primary substations. SCADA monitoring system.
→ Engineering detail in NB11

Road Network Gap

Now: 18 km paved streets. No storm drainage. High dust + erosion. Port access road deteriorated.
Target: 250 km paved by Phase 2. Port access expressway. Sheikh road upgraded to 60 km/h standard.
Gap: Surface: bituminous macadam on primary, interlocking block on secondary. All with kerbs and storm drainage.
→ Engineering detail in NB08

Wastewater & Solid Waste

Now: No sewerage network. Pit latrines. Coastal dumping. Open drainage. 180 t/day solid waste.
Target: Centralised WWTP Phase 2. Reuse of treated effluent for irrigation. Sanitary landfill and recycling.
Gap: 38 km of combined sewer in Phase 1. Decentralised biodigester units for density areas. Marine outfall.
→ Engineering detail in NB08

NetworkX Infrastructure Network Analysis

The networkx library models the water distribution network as a directed graph and the road network as an undirected graph. Maximum flow analysis confirms capacity; betweenness centrality identifies road bottlenecks.

Water Network — Key Results

MetricValue
Network nodes11 (sources + pumps + reservoirs + zones)
Network edges12 (transmission + distribution mains)
Total demand (Phase 3)225,000 m³/day
SWRO supply500,000 m³/day
Max flow SWRO → Burco110,000 m³/day ✓
Pipeline SWRO → Burco320 km
Nodes with alternative pathsPS-1, PS-2, Zone-B, Zone-D
Network connected?Yes

Road Network — Critical Bottlenecks

NodeBetweennessStatusAction
Berbera Junction0.52CRITICALGrade separation required
Sheikh node0.38ImportantCapacity upgrade Phase 1
Old Town junction0.31ImportantBypass route Phase 1
Airport road0.18NormalResurfacing only
BEZ Gate0.15NormalAccess road Phase 1
Betweenness centrality 0–1; higher = more critical. Berbera Junction handles 52% of all flow paths.