Notebook
12
InfrastructureModelled

Water Pipeline Engineering

320 km pipeline · SWRO 500k m³/day Phase 3 · PN63 escarpment engineering · 4 pump stations

320 km
Berbera to Burco
Pipeline length
500,000
m³/day (SWRO)
Phase 3 capacity
1,550 m
coast to escarpment
Elevation gain
PN63
escarpment section
Pressure class
4
× 11 MW solar-powered
Pump stations
USD 0.55
/m³ (vs USD 12 today)
Water tariff

Water Balance — Phase 3

ComponentVolumeSource
SWRO desalination182.5 Mm³/yrSWRO Plant (500k m³/day)
Highland dam catchment+62.4 Mm³/yrDam (136 Mm³ storage)
TOTAL SUPPLY244.9 Mm³/yr—
Berbera urban demand29.2 Mm³/yr80k m³/day × 365
Sheikh + agriculture138.7 Mm³/yrIrrigation dominant
Burco urban supply14.6 Mm³/yrPhase 2 extension
Industrial (BEZ)40.2 Mm³/yrProcess water
TOTAL DEMAND222.7 Mm³/yr—
Annual surplus+22.2 Mm³/yr ✓Safety margin
Dry-season gap (6 months): 19.8 Mm³ · Covered by 136 Mm³ dam (6.9-year buffer)

Pipeline Engineering by Section

SectionLengthPipe specTerrainKey challenge
Coastal plain65 kmDN1200 PCCFlat, 0–50mGravel bedding, salt soil
Escarpment22 kmDN800 steel PN6350–1,550m72–76 bar surge pressure
Highland plateau18 kmDN800 PCC1,550–1,200mRock anchors, bedding
Sheikh–Burco85 kmDN600 PE1001,200–900mGravity, PRVs every 15 km
Urban distribution130 kmDN200–400VariousService connections

⚠ Critical engineering constraint

The escarpment section (22 km, 0 to 1,550m elevation gain) generates surge pressures of 72–76 bar during pump trip events. PN63 carbon steel pipe with surge analysis and PRVs is mandatory. Detailed hydraulic transient analysis is required at feasibility stage.

4 Pump Stations

PS-1
Location
Berbera SWRO plant
Elevation
5 m
Power
11 MW solar
Role
Primary lift — coastal plain section
PS-2
Location
Esc. base, 50m ASL
Elevation
50 m
Power
11 MW solar
Role
Escarpment boost station
PS-3
Location
Mid-escarpment, 800m ASL
Elevation
800 m
Power
11 MW solar
Role
Upper escarpment section
PS-4
Location
Sheikh highland
Elevation
1,550 m
Power
11 MW solar
Role
Highland plateau distribution

Capital Cost Breakdown

ComponentCost
SWRO Plant Phase 1 (50k m³/d)USD 45M
SWRO Phase 2 expansionUSD 180M
SWRO Phase 3 expansionUSD 350M
Pipeline (all sections)USD 280M
Pump stations (×4)USD 44M
Highland damUSD 120M
Urban distributionUSD 65M
TOTAL water systemUSD 1,084M

Revenue at Phase 3

Urban water tariff
USD 100M/yr
USD 0.55/m³
Agricultural water
USD 48M/yr
USD 0.35/m³ (subsidised)
Industrial (BEZ)
USD 22M/yr
USD 1.50/m³
TOTAL water revenue
USD 170M/yr
—

Pipeline Route — Regional Corridor

The 320 km pipeline starts at the SWRO plant on Berbera's coastline, rises 1,550 m through the escarpment, and continues to Sheikh and Burco. Zoom out to see the full Greater Berbera corridor.

Your feedback on this notebook

0/1000 characters

Your feedback is read by the Berbera planning team. All submissions are treated with respect.