Solar Energy System
963 MW Phase 3 · pvlib-validated GHI · CSP + wind + BESS · 1.45 Mt CO₂/yr avoided
pvlib Solar Validation
The pvlib library validates the design GHI figure of 6.4 kWh/m²/day using the Ineichen clear-sky irradiance model for Berbera's exact coordinates (10.432°N, 45.016°E), at the optimal 10.4° tilt angle.
This is a conservative floor: actual irradiance including diffuse and reflected components typically exceeds the clear-sky model value by 5–8%. The 6.4 figure is used throughout all financial modelling.
| Month | GHI (kWh/m²/day) | Peak sun hours | Notes |
|---|---|---|---|
| Jan | 6.8 | 6.8 | Dry season — maximum |
| Feb | 7.1 | 7.1 | Peak month |
| Mar | 7.0 | 7.0 | Pre-monsoon |
| Jun (kharif) | 5.2 | 5.2 | Monsoon cloud reduction |
| Jul (kharif) | 4.8 | 4.8 | Lowest month |
| Aug | 5.1 | 5.1 | Recovery |
| Annual average | 6.4 | 6.4 | Design basis (conservative) |
Energy Build-Out by Phase
| Phase | Solar PV | CSP | Wind | BESS | Output |
|---|---|---|---|---|---|
| Ph1 2026–30 | 355 MW | — | Study | 2 hr LFP | 650 GWh/yr |
| Ph2 2031–35 | 652 MW | — | TBD | 4 hr LFP | 1,170 GWh/yr |
| Ph3 2036–40 | 812 MW | 239 MW | ≤40 MW | 6 hr LFP | 2,250 GWh/yr |
SWRO Energy Check (Phase 1)
Windpowerlib — Escarpment Wind Assessment
windpowerlib models the Sheikh escarpment wind site: 6.5 m/s mean wind speed, air density 1.06 kg/m³, Weibull k=2.1. 20 turbines × 2 MW = 40 MW potential.
LiFePO₄ Battery Storage — 2025/2026 Market Update
| Component | Size | Notes |
|---|---|---|
| Ph1 pump-buffer BESS | 160 MWh (2 hr) | Off-peak pumping, PS4 BESS included |
| Ph2 grid-smoothing BESS | 587 MWh (4 hr) | Evening grid stability + pump dispatch |
| Ph3 alt: BESS replacing CSP | 1,344 MWh (12 hr) | + 244 MW extra PV — alternative to CSP |
| Ph3 CSP baseline | 239 MW molten-salt | CSP costs not falling as fast as BESS |
Why LiFePO₄ (not NMC/NCA) for Berbera
- • Thermal stability: no thermal runaway above 45°C (Berbera ambient is 32–42°C)
- • 6,000-cycle life vs 1,500–2,000 for NMC — critical for daily cycling
- • No cobalt supply risk — aligns with Somaliland/AfDB sustainability criteria
- • Round-trip efficiency: 93–95% (excellent for hot-climate deep-cycle use)
- • Mature supply chain — CATL/BYD/Eve at utility scale, bankable technology
Modern installation profile (2025–26)
- • Container-based BESS (20-ft or 40-ft): plug-and-play, 2–3 MW/container
- • TOPCon bifacial panels: 24–26% efficiency vs 21.5% (NB11 baseline)
- • Single-axis tracking: +15–18% yield vs fixed tilt, standard for utility scale
- • DC-coupled PV+BESS: 3–5% more efficient than AC-coupled
- • BESS delivery leadtime: 6–12 months (was 24 months in 2022)
Libraries: pvlib + windpowerlib
Industry-standard solar modelling library. Uses Ineichen clear-sky model with Linke turbidity factor (Africa/Nairobi timezone). Validates design GHI at 6.4 kWh/m²/day. Chart saved as charts/nb11_pvlib_ghi.png.
Weibull wind distribution (k=2.1, c=7.3 m/s), power curve interpolation for IEC Class II turbine. Capacity factor 0.38 — complementary to solar, reduces BESS requirement. Chart: charts/nb11_windpowerlib.png.
Monthly GHI — Berbera (kWh/m²/day)
Source: pvlib · ERA5 · PVGIS modelled baseline · annual avg 6.9 kWh/m²/day
Jun–Aug Jilaal season shows ~15% reduction; still excellent global radiation resource year-round.
Installed Capacity Build-Out (MW)
Solar + wind vs demand · pvlib/windpowerlib sizing · 963 MW total
Solar Infrastructure — Berbera Urban Area
Infrastructure footprint across the 8,927 ha planning area. Solar generation sites are concentrated in the Z6 BEZ industrial buffer and on suitable flat terrain east of the town centre.